Latest Updates
We are making great progress on the construction and installation of the cable system.
Project Milestones
Project commencement | June 2018 Completed |
Design finalisationLock down of options | September 2018 Completed |
Marine surveyPhysical survey of planned cable route | November 2018 Completed |
Power Feed Equipment (PFE manufacture)Lead-time, manufacture, assembly + test | January 2019 Completed |
Cable manufactureLead-time, manufacture, assembly + test | April 2019 Completed |
Equipment manufactureRepeaters and Branching Units | March 2019 Completed |
Landing facilities and Land Cable Duct RunSydney, Port Moresby, Honiara | July 2019 Completed |
Ship to sitesSydney, Port Moresby, Honiara | August 2019 Completed |
Station InstallationSydney, Port Moresby, Honiara | September 2019 Completed |
Cable main lay1 vessel | October 2019 Completed |
System commissioning1 vessel | December 2019 Completed |