Latest Updates

We are making great progress on the construction and installation of the cable system.

Project Milestones

Project commencement

Read article →

June 2018 Completed

Design finalisation

Lock down of options

September 2018 Completed

Marine survey

Physical survey of planned cable route

Read article →

November 2018 Completed

Power Feed Equipment (PFE manufacture)

Lead-time, manufacture, assembly + test

January 2019 Completed

Cable manufacture

Lead-time, manufacture, assembly + test

Read article →

April 2019 Completed

Equipment manufacture

Repeaters and Branching Units

Read article →

March 2019 Completed

Landing facilities and Land Cable Duct Run

Sydney, Port Moresby, Honiara

July 2019 In Progress

Ship to sites

Sydney, Port Moresby, Honiara

August 2019 In Progress

Station Installation

Sydney, Port Moresby, Honiara

August 2019 Not Started

Cable main lay

1 vessel

October 2019 Not Started

System commissioning

1 vessel

December 2019 Not Started